PRO CONTRACTS PROJECT SHOWCASE

UKZN Rick Turner Student Union Building

Our External Refurbishment at the University of KwaZulu Natal, Howard Campus

Project Details:

Our external refurbishment project at the UKZN Rick Turner building. Here we upgraded the building from lower basement level all the way to the 4th floor – a project which included the installation of louvres , shopfronts and the addition of a new roof.

SCOPE OF WORK:  
Replace Existing Roof Sheeting, Replace All Windows And Doors, Spalling Repairs On Floors, Construct New /Repair External Walls, Install New Louvers, New Mechanical System To Building, Electrical, Painting External And Internal

DURATION: 14 months

PROJECT VALUE: R11.2m